Solent NHS Trust
Refurbishment and Reconfiguration of Hamble House – North & West Wings
Project Description :Refurbishment and Reconfiguration of Hamble House – North & West Wings
Client :Solent NHS Trust
Location :Southsea, Hampshire
Designer :PWP Architects (Building Safety Act Compliance) Currie & Brown (CDM Principal Design
Architects :PWP Architects
Contract Value :£311k
Procurement/contract :JCT MTC Contract
Contract Period :9 Weeks
West End Group delivered the full internal refurbishment and reconfiguration of clinical and administrative areas at Hamble House to enhance NHS service delivery and compliance. Works included:
- Strip out and adaption of 10 therapy rooms in the North Wing, the transformation of the main entrance and clinic rooms into a new reception and waiting
- The creation of secure, fire rated server room within the WEST
- Conversion of the dining and kitchen areas into an open-plan office
- Full refurbishment of existing WC’s, installation of new staff
- General redecoration and ironmongery upgrades
The project was delivered within a live NHS facility, requiring phased works, stakeholder coordination and robust safety and access controls.