SSU – Sir James Matthews Building

Project Description :
The complete refurbishment of 12 Classrooms in an occupied building to provide new learning facility for the new summer school.

Client :
Southampton Solent University

Location :
Southampton, Hampshire

Architect :
Southampton Solent University, Estates Technical Services Department

Contract Value :
£124k

Procurement/contract :
JCT Minor Works Contract 2011

Contract Period :
6 Weeks

Discuss Your Project with Our Team

Project Key Features: 

  • Complete strip out and refurbishment of twelve existing classrooms.
  • Replacement suspended ceiling including installation and rewiring for new energy efficient LED lighting.
  • Re-configuration of power and data to provide new interactive whiteboards to each classroom.
  • Complete decoration of all communal areas and classrooms, including feature wall effect.
  • Replacement carpet with corresponding stripped feature to match wall finish.